023 9247 1029

This was our 2nd project the company has completed in the Channel Islands.

This two week project was completed on 6th August 2016 for Vibe Business Interiors Ltd. (vibe-bi.co.uk)

It has been my most challenging and stressful project this year due to a production delay with fibre on the carpet tiles.

The works involved the installation of 55 sq.m. of ceramic floor tiles, 90 sq.m. of ceramic wall tiles, 50 sq.m. of Forbo Flex loose lay vinyl tiles, and 500 sq.m. of Interface Lima carpet tiles.

The carpet tiles were only just made and boxed on the Wednesday 3rd August at 11pm in Holland, they were transported to the UK and arrived late Thursday afternoon. They were then shipped to Guernsey and arrived on the friday at 11.30pm.  We then received the carpet tiles at 8.30am on the Saturday morning.

I flew over on the Friday afternoon to help my two man team  on the Saturday install 500 sq.m. in two corridors and a large office area,  the carpet tiles were finished at 7.30pm that day, ready for furniture to be installed the next day.