This project in Southampton Town Centre has recently been completed for Vibe Business Interiors Ltd.
Kadampa Meditation Centre was a full refurbishment project that was completed in just 12 weeks.
The sub-floor on this project gave us some real challenges, as the existing floor was extremely uneven.
We used 118 bags of latex screed on the 290 sq.m project, the preparation works took us 7 days to complete and the flooring installation was completed in 5 days.