023 9247 1029

This Project was scheduled in for the summer holidays in August but was finally installed in October 2016.

This 375 sq.m. large multi-purpose space was a newly applied pumped Anhydrite Screed that created a massive headache with the drying time.

After over 200 liters of water was removed from the floor by way of several Dehumidifiers, we were finally able to commence with the flooring.

We applied two coats of F Balls P121 primer, 70 units of Balls 300 self-levelling compound and 2mm Tarkett Granite vinyl sheet which took out team only 6 days to complete.